Project Description

Client:   BUNDIBUGYO DISTRICT LOCAL GOVERNMENT
Location:   Karugutu Sub-county
Type: Rehabilitation of 11.8 KMS of Community Access Roads in Karugutu
Year Completed: 2014
Value: UGX 1,107,757,086

• Site preparation works
• Setting out and Bush Clearing,
• Earthworks,
• Drainage works including bridge construction,
• Gravelling.

The Challenges

• Lack of Equipment, lack of collateral for contract financing and skilled man power.
• Fuel theft by hired operators.
• Supervising Consultant ignorant of the requirements for road works.