20160706_155745

CAIIP3/MASINDI/CAR-BATCHA/Lot 59

House2
interior4

Project Description

Client: Masindi DISTRICT LOCAL GOVERNMENT
Location: Masindi DISTRICT LOCAL GOVERNMENT
Type: Road Construction
Year Completed: 2013
Value: UGX 733,066,723

• Site preparation works
• Setting out and Bush Clearing,
• Earthworks,
• Drainage works including bridge construction,
• Gravelling.

The Challenges

No challenges

IMG-20160621-WA0009

MoLG/DLSP/Works/Oyam/13-14/Lot23

House2
interior4

Project Description

Client: OYAM DISTRICT LOCAL GOVERNMENT
Location: Aber Sub-county, Oyam District
Type: Rehabilitation of 14.8 KMS of Community Access Roads in Aber Sub-county
Year Completed: 2013
Value: UGX 1,143,763,425

• Site preparation works
• Setting out and Bush Clearing,
• Earthworks,
• Drainage works including bridge construction,
• Gravelling

The Challenges

No challenges

20160618_114854

MoLG/DLSP/Works/Oyam/13-14/Lot 58

House2
interior4

Project Description

Client: OYAM DISTRICT LOCAL GOVERNMENT
Location: Aber Sub-county, Oyam District
Type: Rehabilitation of 14.8 KMS of Community Access Roads in Aber Sub-county
Year Completed: 2013
Value: UGX 1,143,763,425

• Site preparation works
• Setting out and Bush Clearing,
• Earthworks,
• Drainage works including bridge construction,
• Gravelling.

The Challenges

No challenges

20160705_105440

DRC/UNHCR/RW-

House2
interior4

Project Description

Client: Danish Refugee Council
Location: Bubukwanga refugee transit camp
Type: Rehabilitation of Community Access Roads in Bubukwanga refugee transit camp
Year Completed: 2013
Value: UGX 148,223,375

• Site preparation works
• Setting out and Bush Clearing,
• Earthworks,
• Drainage works including bridge construction,
• Gravelling.

The Challenges

No serious challenges

IMG-20160624-WA0006

BUND505/WRKS/13-14/00009

House2
interior4

Project Description

Client: BUNDIBUGYO DISTRICT LOCAL GOVERNMENT
Location: Bubukwanga Refugee Transit Camp
Type: Construction of Stabilisation pond
Year Completed: 2013
Value: UGX 154,791,600

• Drainage works
• Excavation of two ponds.
• Cart away excavated material.
• Levelling
• Stone pitching and blinding

The Challenges

• Lack of Equipment, lack of collateral for contract financing and skilled man power.
• Fuel theft by hired operators.
• Supervising Consultant ignorant of the requirements for road works

new_slider02.jpg

CAIIP-2/SOROTI/CAR-BATCH B /LOT 57

House2
interior4

Project Description

Client: SOROTI DSITRICT LOCAL GOVERNMENT
Location: Kateta Sub-county
Type: Rehabilitation of 16.8 KMS of Community Access Roads
Year Completed: 2013
Value: UGX 669,858,788

• preparation Site works
• Setting out and Bush Clearing,
• Earthworks,
• Drainage works,
• Gravelling

The Challenges

• Lack of Equipment, lack of collateral for contract financing and skilled man power.
• Fuel theft by hired operators.
• Supervising Consultant ignorant of the requirements for road works

House2

MoLG/DLSP/Works/Oyam/13-14/Lot23

House2
interior4

Project Description

Client: OYAM DISTRICT LOCAL GOVERNMENT
Location: Aber Sub-county, Oyam District
Type: Rehabilitation of 14.8 KMS of Community Access Roads in Aber
Year Completed: 2014
Value: UGX 1,143,763,425

• Site preparation works
• Setting out and Bush Clearing,
• Earthworks,
• Drainage works including bridge construction,
• Gravelling.

The Challenges

• Poor designs of the roads.
• Unclear instructions from the project Managers